BMD Focus: DOD Space Buys Leak Billions

"DOD originally planned to complete expenditures for SBIRS-High in fiscal year 2005, for example, but currently plans to spend about $3.4 billion in fiscal years 2007 through 2013."

Washington (UPI) Jul 19, 2005
To the American public, U.S. aerospace remains a miracle-working wonder of the world, with bold high tech visionaries at the Pentagon inspiring it to develop ever more fabulous weapons and defenses to keep the United States safe and decades ahead of the rest of the world.

But according to a scathing new report, the Pentagon's space acquisitions policy is a costly and disastrous shambles, routinely incurring 100 percent, and in at least one case even a nearly 300 percent, cost over-runs and failure to deliver the goods.

And this criticism came, not from Democrats or anti-nuclear activists whom space power visionaries routinely shrug off. It came from the Bush administration's own Government Accountability Office.

In testimony before the Strategic Forces Subcommittee of the House Committee on Armed Services delivered last! week, Robert E. Levin, director of Acquisitions and Sourcing Management at the GAO, delivered a devastating critique of the Bush administration and the Pentagon's space acquisitions' record.

"The results are discouraging," he said. "Systems cost more and take much longer to acquire than promised when initially approved.

"Overall, we have found that DOD (the Department of Defense) has been unable to match resources (technology, time, money) to requirements before beginning individual programs, setting the stage for technical and other problems, which lead to cost and schedule increases," Levin said.

Many of the problems, Levin said, came from sloppiness on the part of DOD leaders or senior officials in defining what they specifically wanted their new space-based high-tech systems to do, or in being too visionary -- approving programs when the technology did not yet exist, or had not yet been developed sufficiently to ! assure the necessary reliable performance.

"Technologies are not mature enough (in some cases) to be included in product development," Levin said. "Cost estimates are unreliable -- largely because requirements have not been fully defined and because programs start with many unknowns about technologies."

Levin painted a picture of thousands of hardworking and dedicated individuals stymied by the complexities and cross-purposes of the bureaucratic structures in which they had to function.

"Factors that make it more difficult for DOD to achieve a match between resources and requirements for space acquisitions," he said "... include: a diverse array of organizations with competing interests; a desire to satisfy all requirements in a single step, regardless of the design or technology challenge; and a tendency for acquisition programs to take on technology development that should occur within the S & T (science and technolo! gy) environment."

Also, he said, "DOD starts more programs than it can afford in the long run, forcing programs to underestimate costs and over promise capability."

"As a result," he said, "there is pressure to suppress bad news about programs, which could endanger funding and support, as well as to skip testing because of its high cost."

Levin acknowledged that the Department of Defense "has recently revised its space acquisition policy, in part to attain more knowledge about technologies before beginning an acquisition program."

"However," he continued, "we remain concerned that this policy still allows programs to begin before demonstrating technologies in an operational or simulated environment."

The results of these shortcomings have cost billions of dollars and seriously reduced the space capabilities that the Department of Defense has been able to deliver, Levin said.

"For decades, space acquisition programs have been encountering large cost and increases and schedule delays," he said," As a result, DOD has been unable to deliver capabilities as promised.

"This year alone," Levin said, "... costs have continued to climb on the Space-Based Infrared System High (SBIRS-High) program ... pushing DOD's investment in this critical missile warning system to over $9.9 billion from the initial $3.9 billion made nine years ago."

Also, he said, "the National Polar-orbiting Operational Environmental Satellite System has been restructured and is facing cost increases and schedule delays."

Even the simplest and most straightforward part of the military space program -- launching satellites into space on reliable, cost-effective rockets -- is becoming more difficult and vastly more expensive, Levin warned.

"Unit cost increases for launch vehicles have now increased! by 81 percent since 2002 due to erroneous assumptions about the commercial launch market upon which the program's business case was based," he said.

In the case of many programs, Levin said, there would be no improvement in sight and cost over-runs would continue for many years.

"DOD originally planned to complete expenditures for SBIRS-High in fiscal year 2005, for example, but currently plans to spend about $3.4 billion in fiscal years 2007 through 2013," he said.

Levin and his GAO analysts were not alone in their indictment.

Pedro "Pete" Rustan, director of Advanced Systems and Technology at the National Reconnaissance Office, told a congressional subcommittee, "I think space acquisitions procedures are the biggest challenge facing our space systems today. "We must do things differently."

"Unless decisive actions are taken," Rustan said, "I think we will continue to spend lar! ge amounts of money without returning a commensurate capability to our stakeholders."

Rep. Terry Everett, R-Ala, the subcommittee chairman who called the hearing, made clear he took the criticisms seriously. "Acquisition and management practices, as well as industry standards and quality control must be vastly improved," he said in his opening statement.

Community
Email This Article
Comment On This Article

Related Links
SpaceDaily
Search SpaceDaily
Subscribe To SpaceDaily Express
Military Space News at SpaceWar.com



Memory Foam Mattress Review
Newsletters :: SpaceDaily :: SpaceWar :: TerraDaily :: Energy Daily
XML Feeds :: Space News :: Earth News :: War News :: Solar Energy News


Space Group To Activate New Unit
Colorado Springs CO (SPX) Jan 6, 2006
Air Force Reserve Command's 310th Space Group will travel deeper into the space program when it activates a new unit Jan. 7. Headquarters Reserve National Security Space Institute will be a Reserve associate unit to the National Security Space Institute in Colorado Springs, Colo. The institute is the Department of Defense's focal point for providing education about space power in joint warfighting.







  • Researchers Make Advances In Wind Energy Generation
  • Japan To Seek Ban On All Nuclear Use In NKorea, Even For Power: Media
  • BAE Systems Selected to Develop Humvee on-Board Vehicle Power System
  • Shell's Vast Sakhalin Gas Project To Double To $20B

  • Demand Grows For Nuclear Storages Sites
  • Analysis: Brazil's nuke program
  • Analysis: India-U.S. Nuke Partnership
  • Bush Seeks Full Civil Nuclear Cooperation With India

  • Scientists Seek Sprite Light Source



  • Organic Farms Use Less Energy And Water
  • EU Governments Keep National Bans On GMOs
  • Insects Resistant When Single And Double-Gene Altered Plants In Proximity
  • Insects Developing Resistance To Genetically Engineered Crops

  • Eco-Friendly Motor Rally Sets Off From Kyoto To Celebrate Environment

  • Northrop Grumman to Help NASA Define Requirements for Quiet Sonic Boom Research Aircraft
  • Boeing and Honeywell Sign Contract for Innovative Supply-Chain Solution
  • Raytheon, Cessna Receive NASA Sonic Boom Research Grants
  • New Low Cost Airlines Take Flight In India

  • NASA plans to send new robot to Jupiter
  • Los Alamos Hopes To Lead New Era Of Nuclear Space Tranportion With Jovian Mission
  • Boeing Selects Leader for Nuclear Space Systems Program
  • Boeing-Led Team to Study Nuclear-Powered Space Systems

  • The content herein, unless otherwise known to be public domain, are Copyright 1995-2006 - SpaceDaily.AFP and UPI Wire Stories are copyright Agence France-Presse and United Press International. ESA PortalReports are copyright European Space Agency. All NASA sourced material is public domain. Additionalcopyrights may apply in whole or part to other bona fide parties. Advertising does not imply endorsement,agreement or approval of any opinions, statements or information provided by SpaceDaily on any Web page published or hosted by SpaceDaily. Privacy Statement